Perspective of the Royal Palm Hall facade

More

Hall – A milestone in the Brazilian events industry

The industry has been waiting for a long time for a complex that could bring together all the requirements of a major event:

A large Convention Center, with high quality and flexibility to service your most diverse needs;

Hotels integrated with the Convention Center, offering good value for money stay for your event staff, as well as midscale and luxury options for your delegates;

Extensive meals offer: from a food court to gourmet restaurants;

Privileged logistics: high quality roads, close to an airport with a large air transportation network;

The Royal Palm Hall Conventions Center, the anchor of the Royal Campinas complex offers the most complete events infrastructure in Brazil.

A full-service center: event staff and supervision, full kitchen infrastructure to supply its own catering, ensuring quality and food safety, in addition to of course, a number of modular environments to service all kinds of events.

Datasheet

Hotels

With independent and complementary infrastructure, the hotels part of the complex are ready to receive all audiences of an event, including staff. The integrated solution concept also includes operations: the commercial team can understand all customer needs and offer the most convenient and suitable product, all through just one point of contact.

Privileged Logistics

The Royal Palm Hall is located at the main entrance of Campinas, where the Anhanguera and Santos Dumont Highway meet. Also offers easy access from Bandeirantes and Dom Pedro I highways.

The development’s logistics cause envy to anyone: serviced by the main Brazilian highways, close to the Viracopos International Airport, just 90 km from the city of São Paulo and easily interconnected to the entire countryside of the state.

As part of the counterparties of the development, an overpass will be built over Anhanguera highway, offering direct access to the complex.

Timetable

05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall
05/15 |
Launch of the Foundation Stone
10/15 |
Opening of the Commercial Schedule
11/15 |
Conclusion of Earthworks
12/15 |
Conclusion of Foundation
05/16 |
Conclusion of Pre-frames
05/16 |
Conclusion of External Finish
07/16 |
Conclusion of Metallic Frames
08/16 |
Conclusion of Electrical and Hydraulic systems
09/16 |
Painting of Metallic Frames
09/16 |
Conclusion of covering, Air Conditioner and sprinkler installation
09/16 |
Aerial view of the Royal Palm Hall
11/16 |
Aerial view of the Royal Palm Hall
02/17 |
The works of the Contemporâneo Hotel and Mall are already on the 1st floor
09/17 |
Aerial view of the Royal Palm Hall
06/18 |
Inauguration of the Royal Palm Hall







Royal Campinas